Cuadrilla applied for consent to keep its two Preston New Road wells and Elswick well on 28 March 2022.
The North Sea Transition Authority has looked carefully at this application, alongside recent developments, and agreed to withdraw the requirement to decommission the wells by the end of June.
Cuadrilla now have until the end of June next year to evaluate options for the Preston New Road and Elswick sites. If no credible re-use plans are in place by then, the North Sea Transition Authority expects to reimpose decommissioning requirements.