APPRAISE PHASE, ASSESS PHASE - >6 yrs to 3 yrs before CoP
DEFINE PHASE - >3 yrs before CoP
EXECUTE PHASE - Post-CoP
26 yrs to 3 yrs before CoP - Post-CoP
Strategy alignment (corporate and NSTA)
Cost forecasting & performance benchmarking
>6 yrs to 3 yrs before CoP - >3 yrs before CoP
Learning and knowledge review (inc. technology assessment)
>6 yrs to 3 yrs before CoP
Evaluate asset condition
Infrastructure reuse/repurposing assessment
>3 yrs to 3 yrs before CoP
Contracting/execution strategies
Tendering
Concept development
Develop decom plans
Detailed engineering
Scope aggregation opportunities
3 yrs before CoP - Post-CoP
Implement repurposing/decom prep
Execute repurposing/decom plans
Cost/schedule monitoring
Key activities/milestones:
- Late life operating and decommissioning strategies
- Preliminary cost estimates
- Stakeholder Engagement Plan
- Subsurface basis of design
Key activities/milestones:
- Reuse/repurposing/decom decision
- Refined cost estimate (Class 3)
- Contracting strategy
- Decommissioning Programme (DP) approved by OPRED
Key activities/milestones:
- Execution contracts awarded Further refined cost estimate (Class 2) and schedule
- Permits and consent applications
- Opportunities for execution
ahead of CoP actioned
Key activities/milestones:
- Execution cost and schedule monitoring and risk
- managementProgress reporting (corporate, JV and regulatory)
- Lessons learneddocumenting